Image

We've been working hard over the last month to get the brewery building into shape for the floors to be laid, which will happen next week. Walls have been knocked down, drains installed and kitchens moved. Electrical circuits have been removed and new ones installed, not least of all for the large cold store chillers.

In the background we are also in the process of having our pumpclips designed for our first few beers, T shirt logos designed and our new temperature controlled van should be delivered in the next couple of weeks.

We begin work next week on building the insulated walls and ceiling for the cold store. We will also install the brewery's electrical control systems and installing the Glycol cooling loop for when the fermenters are installed later in the month. All this is working towards being up and brewing sometime in November, and also wholesaling other peoples beer alongside our own, with the Taproom opening sometime before Christmas.

Image